Civil Code Article 502June 19, 2019

If, owing to circumstances for which the undertaker is responsible, the work is completed not within the agreed deadline, or, in the absence of such agreement, or not within a reasonable deadline, the proprietor may demand a reduction in the remuneration or for the injury arising by the delay. "In the case specified in the preceding paragraph, if completion or delivery of the work at a fixed deadline is an essential element of the contract, the proprietor may rescind the contract and demand for the injury arising from failing to perform.